Free NYC Safety Log Templates

Printable, code-referenced PDF logs for the records NYC Building Code Chapter 33 requires you to keep on site — free to download, no email required.

Download the templates

Each template is a letter-size PDF organized around the entries the code and DOB rules require. Print copies for your site binder, or keep a stack in the field office.

BC §3310.8.4 · 1 RCNY §3310-01

Daily Site Safety Log (SSM / SSC)

For major buildings with a designated Site Safety Manager or Coordinator: inspections, meetings, unsafe conditions and corrections, violations and netting work.

PDF · 2 pages · 56 KB

Download PDF
BC §3301.13.13 · 1 RCNY §3301-04

Construction Superintendent Daily Log

Daily inspection record for sites with a registered construction superintendent and no SSM/SSC — date, location and result of each required inspection.

PDF · 1 page · 54 KB

Download PDF
BC §3314.4.4 · §3314.4.3.5

Scaffold Daily Inspection Log

Pre-shift inspection checklist for supported scaffolds: footings, bracing, planking, guardrails, ties, access and power-line clearance, signed by the competent person.

PDF · 1 page (landscape) · 55 KB

Download PDF
BC §3307.6.5

Sidewalk Shed Inspection & Maintenance Log

Installation, adjustment and repair inspections, six-month periodic inspections and routine condition checks for sidewalk sheds, with hazard notification tracking.

PDF · 1 page · 54 KB

Download PDF
1 RCNY §3319-01(k) · §3319-02(j)

Crane & Derrick Jobsite Log

Pre-shift and post-shift inspections by the hoisting machine operator, pre-shift safety meetings, A/D director entries, equipment custody and lift director changes.

PDF · 1 page · 54 KB

Download PDF
BC §3303.8 · FC 312

Standpipe Readiness Log

Readiness inspections, air-pressurized alarm activations and out-of-service / repair tracking for standpipe systems on construction and demolition sites.

PDF · 1 page · 54 KB

Download PDF
Why these logs matter

What the NYC Building Code requires

NYC Building Code Chapter 33 and the DOB rules don't just require safe practices — they require written proof. At major buildings, the Site Safety Manager or Coordinator must keep a site safety log recording every inspection, meeting, unsafe condition, correction and violation, with entries made no later than 7:00 a.m. the following day (BC §3310.8.4, 1 RCNY §3310-01). On smaller permitted jobs, a registered construction superintendent must personally perform daily site inspections and record the date, location and result of each one (BC §3301.13.13, 1 RCNY §3301-04).

Equipment carries its own paper trail. Scaffolds must be inspected daily before each use by a competent person, with a signed record kept on site (BC §3314.4.4). Sidewalk sheds need written inspection reports at installation and every six months thereafter (BC §3307.6.5). Crane and derrick operations require pre-shift and post-shift inspection records, pre-shift meeting entries and custody documentation maintained at the job site (1 RCNY §§3319-01, 3319-02). And standpipe systems must stay in a documented state of readiness, with every alarm activation, inspection and repair logged (BC §3303.8).

Missing or incomplete logs are among the easiest violations for a DOB inspector to write — and among the easiest to prevent. These templates give your field team a consistent format so nothing required goes unrecorded. They are provided as a free resource, are not official DOB forms, and are not a substitute for the code itself: always verify current requirements with the NYC DOB and FDNY.

Need more than a template?

Logs are only one piece of a compliant site. If you're staring down a site safety plan requirement, a superintendent designation, an open violation or a stalled permit, our consultants handle the full picture — filings, plans, coordination and sign-off.

  • Site safety & tenant protection plan development
  • DOB filings, permits and renewals
  • Violation research and resolution
  • Sign-off and Certificate of Occupancy coordination

Using the templates

  1. 1

    Download & print

    Print on standard letter paper. The scaffold log prints landscape.

  2. 2

    Fill in the project header

    Address, BIN, permit holder and the responsible log keeper for the day.

  3. 3

    Record as you go

    Sign and date every entry. Site safety log entries are due by 7:00 a.m. the next day.

  4. 4

    Keep it on site

    Logs must be available at the job site for the Department upon request.