Daily Site Safety Log (SSM / SSC)
For major buildings with a designated Site Safety Manager or Coordinator: inspections, meetings, unsafe conditions and corrections, violations and netting work.
Download PDFPrintable, code-referenced PDF logs for the records NYC Building Code Chapter 33 requires you to keep on site — free to download, no email required.
Each template is a letter-size PDF organized around the entries the code and DOB rules require. Print copies for your site binder, or keep a stack in the field office.
For major buildings with a designated Site Safety Manager or Coordinator: inspections, meetings, unsafe conditions and corrections, violations and netting work.
Download PDFDaily inspection record for sites with a registered construction superintendent and no SSM/SSC — date, location and result of each required inspection.
Download PDFPre-shift inspection checklist for supported scaffolds: footings, bracing, planking, guardrails, ties, access and power-line clearance, signed by the competent person.
Download PDFInstallation, adjustment and repair inspections, six-month periodic inspections and routine condition checks for sidewalk sheds, with hazard notification tracking.
Download PDFPre-shift and post-shift inspections by the hoisting machine operator, pre-shift safety meetings, A/D director entries, equipment custody and lift director changes.
Download PDFReadiness inspections, air-pressurized alarm activations and out-of-service / repair tracking for standpipe systems on construction and demolition sites.
Download PDFNYC Building Code Chapter 33 and the DOB rules don't just require safe practices — they require written proof. At major buildings, the Site Safety Manager or Coordinator must keep a site safety log recording every inspection, meeting, unsafe condition, correction and violation, with entries made no later than 7:00 a.m. the following day (BC §3310.8.4, 1 RCNY §3310-01). On smaller permitted jobs, a registered construction superintendent must personally perform daily site inspections and record the date, location and result of each one (BC §3301.13.13, 1 RCNY §3301-04).
Equipment carries its own paper trail. Scaffolds must be inspected daily before each use by a competent person, with a signed record kept on site (BC §3314.4.4). Sidewalk sheds need written inspection reports at installation and every six months thereafter (BC §3307.6.5). Crane and derrick operations require pre-shift and post-shift inspection records, pre-shift meeting entries and custody documentation maintained at the job site (1 RCNY §§3319-01, 3319-02). And standpipe systems must stay in a documented state of readiness, with every alarm activation, inspection and repair logged (BC §3303.8).
Missing or incomplete logs are among the easiest violations for a DOB inspector to write — and among the easiest to prevent. These templates give your field team a consistent format so nothing required goes unrecorded. They are provided as a free resource, are not official DOB forms, and are not a substitute for the code itself: always verify current requirements with the NYC DOB and FDNY.
Logs are only one piece of a compliant site. If you're staring down a site safety plan requirement, a superintendent designation, an open violation or a stalled permit, our consultants handle the full picture — filings, plans, coordination and sign-off.
Print on standard letter paper. The scaffold log prints landscape.
Address, BIN, permit holder and the responsible log keeper for the day.
Sign and date every entry. Site safety log entries are due by 7:00 a.m. the next day.
Logs must be available at the job site for the Department upon request.